|
Company NameStreetCity, State Postal Code |
Monday, December 30, 2024
First Name Last Name |
e: Email |
Company Name |
t: N/A |
Street |
f: N/A |
City, State Postal Code |
|
Project:
|
Project |
Ref:
|
Reference |
Dear First Name:
According to the contract documents on this project, no interference with our work was shown or detailed in any way. As you know, we have encountered substantial interference in the areas of Areas of Interference and this will confirm that we have been direct to incur additional costs as a result of this interference and that we will look to you for reimbursement of all costs and expenses so incurred. Furthermore, any delays resulting from this additional work will entitle us to a commensurate extension of contract time.
If you have any questions, please do not hesitate to contact me.
Company Name
First Name Last Name
Title
Email
Telephone